| |
La Crosse County Jail |
|
HISTORY |
|
La Crosse County currently uses
two separate buildings for housing inmates. Female inmates
are housed in the "old jail," designed for both male and female
inmates in the mid 1960's, on the second floor of the current
Administrative Center. This linear jail was originally created
with 60 beds plus 10 receiving cells. As the jail population
grew, an area of the first floor in the Administrative Center was
remodeled as a 64 bed male Huber facility. Again the
population grew and in the early 1990's, the former Montgomery Wards
Service Center across the street from the jail, was remodeled
"temporarily" as a 110-bed male Huber facility. The old first
floor Huber area became a "Medium Security" area for male inmates in
the still overcrowded second floor jail. |
| |
|
As the jail population continued
to increase, a decision was made to build a new Law Enforcement
building which would provide housing for inmates along with the
offices and space for the Sheriff's Department, 911 Dispatch, Court
System and District Attorney. The original plan included a
jail facility in excess of 400 beds. The final building
provided 172 beds in the 8-pod (17 to 30 beds per pod) housing unit
on the second floor of the Law Enforcement Center and 23 receiving
cells with a 7-bed medical area (including 2 padded cells) on the
lower level. |
| |
|
Our new jail in the Law
Enforcement Center opened in September 1997. Due to lack of
space and the need for inmates to be housed based on objective
classification, the female population remained in the "old jail,"
which was in need of significant renovation. The County Board
authorized necessary repairs to be made to comply with state
mandates and passed a resolution to limit the number of females to
be held in the facility at a maximum of 39. The "Medium
Security" area in the Administrative Center was closed and the
"temporary" Male Huber Facility remained operational. The
opening of the new jail gave us a total of 321 available beds.
On January 1, 2006 the Male Huber Facility was closed; the bed
capacity was reduced to 211.
In November of 2008, ground was broken
for a 29.5 million dollar addition to the Law Enforcement Center.
Jail expansion plans include a new kitchen, jail garage, booking,
master control, two 57-bed direct supervision blocks, increased
program space and remodeling of three existing pods along with the
medical and receiving holding cell area of the exiting jail. |
|
 |

| Sheriff Steve Helgeson |
| Chief Deputy - Jeff Wolf |
|
|
 |